During 2020 the Tonka Corp. began construction for which it will invoice a total of $ 600,000. The project will end on December 15, 2021.

During 2020 the Tonka Corp. began construction for which it will invoice a total of $ 600,000. The project will end on December 15, 2021. Additional information related to this project is presented below: 2020 2021 Costs incurred in the period $ 225,000 $ 255,000 Estimated costs to complete the project 225,000 Customer Billing 240,000 360,000 Cash Received from Clients 200,000 400,000 Assuming Since Tonka uses the completed contract method, how much will the 2021 gross profit be related to this project?

a $ 45,000

b. $ 120,000

c $ 80,000

d 75,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Company Accounting

Authors: Ken Leo, Jeffrey Knapp, Susan McGowan, John Sweeting

11th Edition

0730344770, 9780730344773

More Books

Students also viewed these Accounting questions