During 2023, Hoang Corporation started a construction job with a contract price of $4.2 million. Hoang ran into severe technical difficulties during construction but managed
During 2023, Hoang Corporation started a construction job with a contract price of $4.2 million. Hoang ran into severe technical difficulties during construction but managed to complete the job in 2025. | |||||||||||||||
The contract is non-cancellable. Under the terms of the contract, Hoang sends billings as revenues are earned. Billings are non-refundable. The following information is available: | |||||||||||||||
2023 | 2024 | 2025 | |||||||||||||
Costs incurred to date | 600000 | 2100000 | 4100000 | ||||||||||||
Estimated costs to complete | 3150000 | 2100000 | 0 | ||||||||||||
Billings for the year | 1000000 | 2000000 | 1200000 | ||||||||||||
Cash Collections for the year | 800000 | 3000000 | 400000 | ||||||||||||
Calculate the amount of gross profit that should be recognized each year under the percentage-of-completion method using the schedule outlined in class. | |||||||||||||||
Calculate the amount of gross profit or loss that should be recognized each year under the completed-contract method. Explain the treatment of losses under the completed-contract method. | |||||||||||||||
Prepare the year-end journal entries for 2024 to record revenues and expenses from the contract, and the billings and collections assuming the percentage-of-completion method is used. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started