Answered step by step
Verified Expert Solution
Question
1 Approved Answer
During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and
During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented in the lessons learned. What should the project manager do? Check with the team to learn what can be done, and consult an expert. Check that this information was documented correctly. Meet with the sponsor to ask for their support. Ask the sponsor to close the project and pay the contracted penalty
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started