During a sprint planning meeting, an Agile team member suggests adding a component to a project, which is beyond the scope of the work. Adding
During a sprint planning meeting, an Agile team member suggests adding a component to a project, which is beyond the scope of the work. Adding an extra component in a project is an example of which of the following?,During a sprint planning meeting, an Agile team member suggests adding a component to a project, which is beyond the scope of the work. Adding an extra component in a project is an example of which of the following? Grooming,Refactoring,D,C,Progressive elaboration