During a typical week, hospital surgery department has 12 operating room (OR) hours , 48 surgeons , and 40 nurses . To conduct a surgery
During a typical week, hospital surgery department has 12 operating room (OR) hours, 48 surgeons, and 40 nurses. To conduct a surgery for a patient, the needed resources are:
2 operating room hours per surgery
4 surgeons per surgery
5 nurses per surgery to support the surgeon
Based on our resource capacities, how many patients can receive a surgery at the same time? (in other words, what is the maximum output?)
Answer = Surgeries / Week
What is the utilization of each of the resources at the maximum output? (Approximate your answers to four decimal places)
UtilizationOR-Hours = %
UtilizationSurgeons = %
UtilizationNurses = %
Which is the bottleneck resource? In other words, which resource runs out, and prevents us from conducting more surgeries?
Bottleneck: OR Hours Surgeons Nurses (Select One of these)
If I could hire 3 additional surgeons, whats the new system capacity and new utilization of Surgeons?
New system capacity = Surgeries/Hour
New utilization of Surgeons = %
Instead, if I could increase operating hours by 14 hours, whats the new system capacity and new utilization of OR Hours? In that case, which resource is the new bottleneck?
New system capacity = Surgeries/Hour
New utilization of OR Hours = %
New bottleneck: OR Hours Surgeons Nurses (select One)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started