During March 2014, Toby Tool & Die Company worked on four jobs. A review of direct labor costs reveals the following summary data. Actual Standard
During March 2014, Toby Tool & Die Company worked on four jobs. A review of direct labor costs reveals the following summary data.
Actual | Standard | ||||||||||
Job Number | Hours | Costs | Hours | Costs | Total Variance | ||||||
A257 | 216 | $5,184 | 221 | $5,304 | $ 120 | F | |||||
A258 | 431 | 11,637 | 419 | 10,056 | 1,581 | U | |||||
A259 | 301 | 7,676 | 302 | 7,248 | 428 | U | |||||
A260 | 116 | 2,552 | 108 | 2,592 | 40 | F | |||||
Total variance | $1,849 | U |
Analysis reveals that Job A257 was a repeat job. Job A258 was a rush order that required overtime work at premium rates of pay. Job A259 required a more experienced replacement worker on one shift. Work on Job A260 was done for one day by a new trainee when a regular worker was absent. Prepare a report for the plant supervisor on direct labor cost variances for March. (Round quantity variance, actual rate, standard rate and price variance to 2 decimal places, e.g. 10.50.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started