During May, Joliet Fabrics Corporation manufactured 530 units of a special multilayer fabric with the trade name Stylex. The following information from the Stylex production
During May, Joliet Fabrics Corporation manufactured 530 units of a special multilayer fabric with the trade name Stylex. The following information from the Stylex production department also pertains to May.
Direct material purchased: 18,300 yards at $1.41 per yard $ 25,803
Direct material used: 9,800 yards at $1.41 per yard 13,818
Direct labor: 2,400 hours at $9.18 per hour 22,032
The standard prime costs for one unit of Stylex are as follows:
Direct material: 20 yards at $1.38 per yard $ 27.60
Direct labor: 4 hours at $9.00 per hour 36.00
Total standard prime cost per unit of output $ 63.60
Required: Compute the following variances for the month of May. (Indicate the effect of each variance by selecting "Favorable" or "Unfavorable". Select "None" and enter "0" for no effect (i.e., zero variance).
Direct Material Price Variance:
Direct Material Quantity Variance:
Direct Material Purchase Price Variance:
Direct Labor Rate Variance:
Direct Labor Efficiency Variance:
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started