During one 12-hour shift, 800 non-defective parts are desired from a fabrication operation. The standard time for the operation is 18 minutes. Because the machine

During one 12-hour shift, 800 non-defective parts are desired from a fabrication operation. The standard time for the operation is 18 minutes. Because the machine operations are unskilled, the actual time it takes to operate is 20 minutes, and on average, 10% of the parts that begin fabrication are scrapped. 


Assuming that each of the machines used for this operation will not be available for two hours each shift, determine the number of machines required.

Step by Step Solution

3.36 Rating (146 Votes )

There are 3 Steps involved in it

Step: 1

To determine the number of machines required lets break down the problem step by step First lets cal... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting

Authors: Carl S. Warren, James M. Reeve, Jonathan Duchac

26th edition

128574361X, 978-1305446052, 1305446054, 978-1285743615

More Books

Students also viewed these General Management questions