During preparation for work on the construction site, the contractor installs additional temporary lighting, signs and handrails to decrease the probability of injuries onsite. More
During preparation for work on the construction site, the contractor installs additional temporary lighting, signs and handrails to decrease the probability of injuries onsite. More overnight work is being planned than on previous projects. The contractor is using which risk response strategy? Question 1 options: Avoid Mitigate Enhance Transfer Exploit Escalate Accept Share