During release planning two key stakeholders have a disagreement about the priority of certain user stories. Who should resolve this issue? a. The key stakeholder
During release planning two key stakeholders have a disagreement about the priority of certain user stories. Who should resolve this issue? a. The key stakeholder in question if they cannot resolve it then the whole team should step in to try and resolve it b. the self organizer agile team c. the product owner d. the team facilitator
Step by Step Solution
There are 3 Steps involved in it
Step: 1