Question
1 Approved Answer
During risk planning, you encounter a risk that you find difficult to manage. Therefore, you make small changes to your project management plan to eliminate
During risk planning, you encounter a risk that you find difficult to manage. Therefore, you make small changes to your project management plan to eliminate the risk. Which risk response strategy are you using here? a Avoid b Mitigate c Accept d Exploit
Step by Step Solution
There are 3 Steps involved in it
Step: 1