Question

1 Approved Answer

During the campus Spring Fling, the bumper car amusement attraction has a problem of cars becoming disabled and in need of repair. Repair personnel can

During the campus Spring Fling, the bumper car amusement attraction has a problem of cars becoming disabled and in need of repair. Repair personnel can be hired at the rate of $20 per hour, but they only work as one team. Thus, if one person is hired, he or she works alone; two or three people work together on the same repair.

One repairer can fix cars in an average time of 45 minutes. Two repairers take 30 minutes, and three take 20 minutes. While these cars are down, lost income is $40 per hour. Cars tend to break down at the rate of 1.00 per hour.

Management is trying to decide how many repair persons to hire, and has asked you for cost data.

a. What is the total hourly cost with one repair person? (Round your intermediate calculations and final answer to 2 decimal places.)

Total cost per hour $

b. What is the total hourly cost with two repair persons? (Round your intermediate calculations and final answer to 2 decimal places.)

Total cost per hour $

c. What is the total hourly cost with three repair persons? (Round your intermediate calculations and final answer to 2 decimal places.)

Total cost per hour $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Analysing The Value Proposition Of The Audit Process In Africa The Case Of Malawi

Authors: Daniel Dunga

1st Edition

3659166286, 978-3659166280

More Books

Students also viewed these Accounting questions