During the evaluation of the project, you found that the total planned costs of your project were $ 4 0 0 , 0 0 0

During the evaluation of the project, you found that the total planned costs of your project were $400,000. The actual costs were $220,000. How can you describe the project performance?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: William J Stevenson

12th edition

2900078024107, 78024102, 978-0078024108

More Books

Students also viewed these General Management questions

Question

Explain the conditions necessary for the growth of fungi?

Answered: 1 week ago

Question

Plato concept of justice ?

Answered: 1 week ago

Question

Plato Theory of Education?

Answered: 1 week ago