Question
1 Approved Answer
During user testing a client agreed to a final product. A few days later the client is reconsidering their agreement. What should the project manager
During user testing a client agreed to a final product. A few days later the client is reconsidering their agreement. What should the project manager do? Select one.
A. Refer to the project's project charter.
B. Review the project's acceptance criteria.
C. Review the requirements documentation.
D. Refer to the project's quality management plan.