During year 1, Meriwether Construction Company started a construction job with a contract price of $3,000,000. The job was completed in year 2 and the
During year 1, Meriwether Construction Company started a construction job with a contract price of $3,000,000. The job was completed in year 2 and the company uses the percentage of completion method. The following information is available for year 1 and year 2:
Year 1 | Year 2 | |
Cost incurred to date | $500,000 | $2,400,000 |
Estimated cost to complete | 1,500,000 | 0 |
Billings to date | 300,000 | 1,800,000 |
Collections to date | 100,000 | 1,600,000 |
What amount of gross profit should Meriwether recognize for this job for year 2?
A. $1,000,000
B. $250,000
C. $350,000
D. $600,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started