Dynando Incorporated planned to use materials of $8 per unit but actually used materials of $16 per unit, and planned to make 1640 units but
Dynando Incorporated planned to use materials of $8 per unit but actually used materials of $16 per unit, and planned to make 1640 units but actually made 1770 units The flexible-budget variane for materials is O $14,160 favorable $13,120 favorable O $13,120 unfavorable O $14,160 unfavorable