E 622 Long-term contract; revenue recognition upon project completion; loss projected on entire project On February 1, 2021, Arrow Construction Company entered into a three-year

E 622 Long-term contract; revenue recognition upon project completion; loss projected on entire project

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000.

In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of $3,800,000 were incurred. The companys fiscal year-end is December 31. This project does not qualify for revenue recognition over time.

Please be descriptive

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost Accounting

Authors: M.E. Thukaram Rao

3rd Edition

8122433820, 978-8122433821

More Books

Students also viewed these Accounting questions