E Page 513 7. The following data have been collected for a British healthcare IT project for two-week reporting periods 2 through 12. Compute the
E Page 513 7. The following data have been collected for a British healthcare IT project for two-week reporting periods 2 through 12. Compute the SV, CV, SPI, and CPI for each period. Plot the EV and the AC on the summary graph provided. Plot the SPI. CPI, and PCIB on the index graph provided. (You may use your own graphs.) What is your assessment of the project at the end of period 12? 000 4 2 12 2 2 6 8 14 1 4 4 3 10 10 5 14 0 0 4 6 10 4 14 6 16 2 2 2 6 4 10 10 8 18 14 7 18 14 4 18 18 8 221 0 18 4 22 Legend ES ID EF SL SL LS DUR LF Page 514 PV Task DUR ES LF SL ($00) 0 2 Baseline (PV) ($00) 4 6 8 10 12 14 16 18 20 22 1 4 4 8 4 A 2 8 3 4 6 4 14 4 111 OOO 2 40 10 30 10 4 4 4 10 2 20 10 199 10 10 10 10 10 10 15 5 5 4 10 14 0 40 20 20 9 8 8 18 2 60 20 20 10 10 7 4 14 18 0 20 10 10 8 4 18 22 30 20 10. Period PV total 4 4 30 35 35 50 30 20 10 20 10 Cumulative PV totali 4 8 38 73 108 158 188 208 218 238 248 Status Report: Ending Period 2 Task 1 ($00) %Complete EV AC PV CV SV 50% Cumulative Totals Status Report: Ending Period ($00) Task %Complete EV AC PV CV SV 1 Finished 10 Cumulative Totals 10 Status Report: Ending Period 6 %Complete EV AC PV CV SV ($00) Task I Finished 10- 2 25% 15 3 33% 12 4 0% Cumulative Totals Status Report: Ending Period 8 Task 1 37 (500) %Complete EV AC PV CV SV Finished 10 30% 20 Status Report: Ending Period 2 ($00) %Complete EV AC PV CV SV Task 1 50% Cumulative Totals Status Report: Ending Period 4 Task 4 ($00) %Complete EV AC PV CV SV Finished 10 Cumulative Totals 10 Status Report: Ending Period 6 ($00) Task %Complete EV AC PV CV SV 1 Finished 2 25% 95 10 15 3 33% 12 4 0% 0 Cumulative Totals Status Report: Ending Period 8 Task %Complete EV AC PV CV SV 37 (500) Finished 10 2 30% 20 3 Cumulative Totals 60% - 25- 0% 55 ($00) Status Report: Ending Period 10 %Complete EV AC PV CV SV Finished Task 1 10 2 60% 30 3 Finished 40 4 50% 20 5 0% 6 30% 24 Cumulative Totals Status Report: Ending Period 12 Task %Complete EV AC PV CV SV 124 ($00) Finished 10 2 Finished 50 3 Finished 40 4 Finished 40 50% 30 50% 40 Cumulative Totals Period SPI CPI PCIB 2 8 10 12 - 210 SPI - EV/PV CPI - EV/AC PCIB = EV/BAC 260 240 220 200 180 160 Dollars ($00) 140 120 100 80 60 40 20 0 PV 6 8 10 12 14 16 18 20 22 24 1.60 1.40 1.20 1.00 80 Index 60 40 20 0 2 4 I I 1 8 9 I B t I T T 10 12 14
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started