E - Reserve Problem 6 - 1 West Whiteland Township uses the calendar year. It decides to extend sewer lines to a recently developed subdivision.

E-Reserve Problem 6-1
West Whiteland Township uses the calendar year. It decides to extend sewer lines to a
recently developed subdivision. The township estimates the cost will be $8.0 million. The
project is to be funded first with the issuance of $5.0 million in special assessment bonds;
second with a $2.0 million reimbursement grant from the state; and finally with a $1.0
million pledge (contribution) from ABC Construction Company to cover any additional
expenses. The agreement with the state is that it will award the reimbursement grant to West
Whiteland Township only after $5.0 million is spent. During 2023, West Whiteland
Township engages in the following transactions, all of which are recorded in the Capital
Projects Fund.
1. The township issues $5.0 million in bonds at a premium of $.40 million and incurs $.18
million in issue costs. The premium, net of issue costs, is transferred to a newly
established debt service fund.
2. The township receives $2.0 million in cash from the state for the reimbursement grant in
anticipation that the township will incur at least $2.0 million in construction costs.
3. The township pays $5.9 million to invest in short-term (less than one year) securities.
4. The township issues purchase orders and signs construction contracts for $7.9 million.
5. The township sells $4.0 million of its investments for $4.4 million.
6. The township receives invoices totaling $6.2 million. As permitted by its agreement with
its prime contractor, the township retains $.7 million pending satisfactory completion of
the project. The township pays $5.5 million.
7. The township recognizes the revenue earned from the reimbursement grant.
8. Anticipating that the project will be completed in the following year, ABC Construction
Company pledges to contribute $1 million to West Whiteland Township. The township
receives the contribution as follows:
$700,000 in 2023;
$100,000 in January, 2024;
$100,000 in February, 2024; and
$100,000 in March, 2024.
9. By year-end, the investments still on hand decreased in value by $.25 million.
Do
a. Using good form, prepare journal entries to record the transactions in 2023.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Top Accounting And Auditing Issues For 2023

Authors: CCH Tax Law Editors

1st Edition

0808059335, 978-0808059332

More Books

Students also viewed these Accounting questions