e . Total of direct costs In any construction project cash flow, the total payments ( total cash - out ) in the cash module
e Total of direct costs
In any construction project cash flow, the total payments total cashout in the cash module must equal: points
a Project estimate
b Project contract amount
c Cost loaded schedule
d Total of all indirect costs
e Total of all direct costs
Effective cash needed for a project before payment is received from the owner for the month of May will be positive in which scenario. points
a When total cash generated in April will be positive and less than the cash needed for the project before payment is received from the owne
during May.
b When total cash generated in April will be positive, and more than the cash needed for the project before payment is received from the
owner during May.
c When total cash generated in May will be positive, and more than the cash needed for the project before payment is received from the
owner during May.
d Never
e All of the above
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started