E11-8 Compute the materials, labor variances, and list reasons for unfavorable variances . AN following direct materials and direct labor data pertain to the operations
E11-8
Compute the materials, labor variances, and list reasons for unfavorable variances.
AN following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August.
Costs
Quantities
Actual labor rate
$13 per hour
Actual hours incurred and used
4,150 hours
Actual materials price
$128 per ton
Actual quantity of materials purchased and used
1,220 tons
Standard labor rate
$12.50 per hour
Standard hours used
4,300 hours
Standard materials price
$130 per ton
Standard quantity of materials used
1,200 tons
Instructions
a. Compute the total, price, and quantity variances for materials and labor.
b.Provide two possible explanations for each of the unfavorable variances calculated above, and suggest where responsibility for the unfavorable result might be placed.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started