Question
E2-18 (Algo) Calculating Actual and Applied Manufacturing Overhead Costs and Over- or Underapplied Overhead Costs [LO 2-3, 2-4, 2-5, 2-6] Verizox Company uses a job
E2-18 (Algo) Calculating Actual and Applied Manufacturing Overhead Costs and Over- or Underapplied Overhead Costs [LO 2-3, 2-4, 2-5, 2-6]
Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $193,000. Estimated direct labor cost was $478,640 for 19,300 hours.
Actual costs for the most recent month are summarized here:
Item Description | Total Cost | |
Direct labor (1,930 hours) | $ | 47,865 |
Indirect costs | ||
Indirect labor | 2,540 | |
Indirect materials | 3,450 | |
Factory rent | 3,210 | |
Factory supervision | 4,840 | |
Factory depreciation | 5,600 | |
Factory janitorial work | 1,280 | |
Factory insurance | 1,790 | |
General and administrative salaries | 4,240 | |
Selling expenses | 5,340 | |
Required: 1. Calculate the predetermined overhead rate.
2. Calculate the amount of applied manufacturing overhead.
3. Calculate actual manufacturing overhead costs.
4. Compute over- or underapplied overhead.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3