Question

1 Approved Answer

Each eight-hour day the assembly line produces 1600 units that essembly multiple individual components together. Because the assembly line is located in a different area

Each eight-hour day the assembly line produces 1600 units that essembly multiple individual components together. Because the assembly line is located in a different area of the plant than the areas where the components are produced, a two-card (C and P) pull system is used. The information about producing and moving component A is as:

Container size 60

Conveyance waiting time 1.00 hour

Conveyance total move time 0.50 hour

Assuming no safety margin is to be maintained, how many conveyance kanban cards are needed for component A? Round up the whole number

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Social Media Management

Authors: Ben Shields

1st Edition

019029633X, 978-0190296339

More Books

Students also viewed these General Management questions

Question

DO CONTRACT WORKERSGETTHE SAME ENTITLEMENTS AS EMPLOYEES?

Answered: 1 week ago

Question

2.5 Describe the purpose of employment equity programs.

Answered: 1 week ago