Each X requires 2 of component Y; each Y requires 4 of part Z. The lead time for assembly of X is 1 week.
Each X requires 2 of component Y; each Y requires 4 of part Z. The lead time for assembly of X is 1 week. The lead time for the manufacture of Y is 1 week. The lead time for the procurement of Z is 6 weeks. The cumulative lead time for X is weeks. 10 cannot be determines