Early in your project a preliminary list of risks was developed. You have created a more detailed list of risks for further study. You have
Early in your project a preliminary list of risks was developed. You have created a more detailed list of risks for further study. You have not scheduled a time to work through this set of risks, because key people who will help you have not yet informed you of their availability. Creating the more detailed list of risks is an output of which process?
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis.
Plan Risk Management
Identify Risks