Earned value analysis is a powerful monitoring tool. Assume a task with BCWS of $2500, BCWP of $1000 and task actual cost of $800. Which
Earned value analysis is a powerful monitoring tool. Assume a task with BCWS of $2500, BCWP of $1000 and task actual cost of $800. Which of the following statements are true: I. The task is over budget; II. The task is behind schedule. Group of answer choices Both I and II are true Only I is true Only II is true Neither I nor II is true