Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly ) and progress in an objective manner in terms

Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value). The data identified below was listed in the projects status report:

Planned Value of work (PV) = $70,000

Earned Value of work performed (EV) = $50,000

Actual Cost of work performed (AC) = $75,000

Original Planning:

Budgeted cost At Completion (BAC) = $100,000

Original length of the project is 15 months

Using the data, calculate the following:

a). Cost Performance Index (CPI). (2 marks)

b). Schedule Performance Index (SPI). (2 marks)

c). Expected cost At Completion (EAC). (2 marks)

d). The money needed from the time of the report to complete the project i.e., Estimate at Completion (ETC). (2 marks)

e). The Schedule Variance (SV). (2 marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Finance questions