Question

1 Approved Answer

Earned Value, S - Curve Known: Total Budget = $ 2 5 , 0 0 0 BCWS = $ 8 , 3 3 3 B

Earned Value, S-Curve
Known:
Total Budget =$25,000
BCWS =$8,333
BCWP=$6,400
ACWP =$7,800
Project Duration =40 days
Data Date =10 days
A) Perform following analyses of project based on data above.
What is the Cost Variance?
What is the Schedule Variance?
B) Plot S-Curve showing CV and SV.
C) Review results and explain project status.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Management

Authors: Andrew J DuBrin

10th Edition

0996757872, 9780996757874

More Books

Students also viewed these General Management questions

Question

=+b) Is MediaChips manufacturing process in control?

Answered: 1 week ago

Question

Relax your shoulders

Answered: 1 week ago

Question

Keep your head straight on your shoulders

Answered: 1 week ago

Question

Be straight in the back without blowing out the chest

Answered: 1 week ago