Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Earned-value analysis. A project budget calls for the following expenditures: Task Date Budgeted Amount Build forms April 1 $10,000 April 1 $50,000 Pour foundation May

image text in transcribed

Earned-value analysis. A project budget calls for the following expenditures: Task Date Budgeted Amount Build forms April 1 $10,000 April 1 $50,000 Pour foundation May 1 $100,000 May 1 $30,000 Frame walls June 1 $30,000 Remaining tasks July 1 and beyond $500,000 Define each term in your own words, calculate these values for the above project, and show your work: 1. Budgeted cost baseline (make a graph illustrating this one) 2. Budget at completion (BAC) 3. Planned value (PV) as of May 1 4. Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule. 5. SV as of May 1. 6. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1. 7. Schedule performance index (SPI) 8. Cost performance index (CPI) 9. Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs 10. Estimate at completion (EAC)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles Of Auditing And Other Assurance Services

Authors: Ray Whittington, Kurt Pany

13th Edition

007232726X, 9780072327267

More Books

Students also viewed these Accounting questions