Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

eBook A mining company is considering a new project. Because the mine has received a permit, the project would be legal; but it would cause

image text in transcribed
image text in transcribed
eBook A mining company is considering a new project. Because the mine has received a permit, the project would be legal; but it would cause significant harm to a nearby river. The firm could spend an additional $11 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. Developing the mine (without mitigation) would require an initial outlay of $69 million, and the expected cash inflows would be $23 million per year for 5 years. If the firm does invest in mitigation, the annual inflows would be $24 million. The risk-adjusted WACC is 13%. O O E a. Calculate the NPV and IRR with mitigation. Enter your answer for NPV in millions. For example, an answer of $10,550,000 should be entered as 10:55. Do not round intermediate calculations. Round your answers to two decimal places. NPV: $ IRR: CO O million % Calculate the NPV and IRR without mitigation. Enter your answer for NPV in millions. For example, an answer of $10,550,000 should be entered as 10.55. Do not round intermediate calculations. Round your answers to two decimal places. NPV: S IRR: b. How should the environmental effects be dealt with when this project is evaluated? % million 1. The environmental effects if not mitigated could result in additional loss of cash flows and/or fines and penalties due to ill will among customers, community, etc. Therefore, even though the mine is legal without mitigation, the company needs to make sure that they have anticipated all costs in the "no mitigation analysis from not doing the environmental mitigation. II. The environmental effects should be ignored since the mine is legal without mitigation. 111. The environmental effects should be treated as a sunk cost and therefore ignored. IV. The environmental effects if not mitigated would result in additional cash flows. Therefore, since the mine is legal without mitigation, there are no benefits to performing a "no mitigation analysis. V. The environmental effects should be treated as a remote possibility and should only be considered at the time in which they actually occur -Select- A-2 10 b. How should the environmental effects be dealt with when this project is evaluated? 1. The environmental effects if not mitigated could result in additional loss of cash flows and/or fines and penalties due to ill will among customers, community, etc. Therefore, even though the mine is legal without mitigation, the company needs to make sure that they have anticipated all costs in the "no mitigation" analysis from not doing the environmental mitigation. II. The environmental effects should be ignored since the mine is legal without mitigation. III. The environmental effects should be treated as a sunk cost and therefore ignored. TV. The environmental effects if not mitigated would result in additional cash flows. Therefore, since the mine is legal without mitigation, there are no benefits to performing a "no mitigation" analysis. * V. The environmental effects should be treated as a remote possibility and should only be considered at the time in which they actually occur -Select- D c. Should this project be undertaken? -Select- If so, should the firm do the mitigation? 1. Under the assumption that all costs have been considered, the company would not mitigate for the environmental impact of the project since its IRR without mitigation is greater than its IRR when mitigation costs are included in the analysis. II. Under the assumption that all costs have been considered, the company would mitigate for the environmental impact of the project since its NPV with mitigation is greater than its NPV when mitigation costs are not included in the analysis. III. Under the assumption that all costs have been considered, the company would not mitigate for the environmental impact of the project since its NPV without mitigation is greater than its NPV when mitigation costs are included in the analysis. IV. Under the assumption that all costs have been considered, the company would mitigate for the environmental impact of the project since its IRR with mitigation is greater than its IRR when mitigation costs are not included in the analysis. V. Under the assumption that all costs have been considered, the company would not mitigate for the environmental impact of the project since its NPV with mitigation is greater than its NPV when mitigation costs are not included in the analysis. -Select- A-Z 10

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Real Life Money An Honest Guide To Taking Control Of Your Finances

Authors: Clare Seal

1st Edition

1472272293, 978-1472272294

More Books

Students also viewed these Finance questions