Answered step by step
Verified Expert Solution
Question
1 Approved Answer
eBook Print Item Capital Expenditures Budget On January 1, 2012, the controller of Omicron Inc. is planning capital expenditures for the years 2012-2015. The
eBook Print Item Capital Expenditures Budget On January 1, 2012, the controller of Omicron Inc. is planning capital expenditures for the years 2012-2015. The following interviews helped the controller collect the necessary information for the capital expenditures budget: Director of Facilities: A construction contract was signed in late 2011 for the construction of a new factory building at a contract cost of $10,000,000. The construction scheduled to begin in 2012 and be completed in 2013. Vice President of Manufacturing: Once the new factory building is finished, we plan to purchase $1.5 million in equipment in late 2013. I expect that an additional $200,000 will be needed early in the following year (2014) to test and install the equipment before we can begin production. If sales continue to grow, I expect we'll nee to invest another $1,000,000 in equipment in 20YS. Chief Operating Officer: We have really been growing lately. I wouldn't be surprised if we need to expand the size of our new factory building in 2015 by at least 35%. Fortunately, we expect inflation to have minimal impact on construction costs over the next four years. In addition, I would expect the cost of the expansion to be proportional to the size of the expansion. Director of Information Systems: We need to upgrade our information systems to wireless network technology. It doesn't make sense to do this until after the new factor building is completed and producing product. During 2014, once the factory is up and running, we should equip the whole facility with wireless technology. I think it would cost us $800,000 today to install the technology. However, prices have been dropping by 25% per year, so it should be less expensive at a later date. Chief Financial Officer: I am excited about our long-term prospects. My only short-term concern is managing our cash flow while we expend the $4,000,000 of construction costs on the portion of the new factory building scheduled to be completed in 2012. Use this interview information to prepare a capital expenditures budget for Omicron Inc. for the years 2012-2015. Enter all amounts as positive numbers. Omicron Inc. Capital Expenditures Budget For the Four Years Ending December 31, 20Y2-2015 Building Equipment Information systems Total 2012 2013 2014 2015 000 000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started