Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

eBook Question Content Area Basics of Variance Analysis, Variable Inputs Basuras Waste Disposal Company has a long-term contract with several large cities to collect garbage

eBook

Question Content Area

Basics of Variance Analysis, Variable Inputs

Basuras Waste Disposal Company has a long-term contract with several large cities to collect garbage and trash from residential customers. To facilitate the collection, Basuras places a large plastic container with each household. Because of wear and tear, growth, and other factors, Basuras places about 230,000 new containers each year (about 20% of the total households). Several years ago, Basuras decided to manufacture its own containers as a cost-saving measure. A strategically located plant involved in this type of manufacturing was acquired. To help ensure cost efficiency, a standard cost system was installed in the plant. The following standards have been established for the product's variable inputs:

Standard Quantity Standard Price (rate in $) Standard Cost
Direct materials 12 lbs. $ 3.5 $42
Direct labor 1.7 hrs. 13 22.1
Variable overhead 1.7 hrs. 5 8.5
Total $64.1

During the first week in January, Basuras had the following actual results:

Units produced 10,000
Actual labor costs $228,800
Actual labor hours 17,600
Materials purchased and used 118,000 lbs. @ $3.55
Actual variable overhead costs $ 110,500

The purchasing agent located a new source of slightly higher-quality plastic, and this material was used during the first week in January. Also, a new manufacturing process was implemented on a trial basis. The new process required a slightly higher level of skilled labor. The higher-quality material has no effect on labor utilization. However, the new manufacturing process was expected to reduce materials usage by 0.25 pound per container.

Required:

1. Conceptual Connection: Compute the materials price and usage variances. Assume that the 0.25 pound per container reduction of materials occurred as expected and that the remaining effects are all attributable to the higher-quality material. Would you recommend that the purchasing agent continue to buy this quality, or should the usual quality be purchased? Assume that the quality of the end product is not affected significantly.

Price $fill in the blank 1

FavorableUnfavorableNeitherUnfavorable

Usage $fill in the blank 3

FavorableUnfavorableNeitherFavorable

Select the effect.

The new process saves money.The new process costs more money.The new process saves money.

Enter the net amount of the effect. $fill in the blank 6
Select the correct decision.

Use the higher-quality material.Use the original material.Use the original material.

2. Conceptual Connection: Compute the labor rate and efficiency variances. Assuming that the labor variances are attributable to the new manufacturing process, should it be continued or discontinued? In answering, consider the new process's materials reduction effect as well. If an amount is zero, enter "0".

Rate $fill in the blank 8

FavorableUnfavorableNeitherNeither

Efficiency $fill in the blank 10

FavorableUnfavorableNeitherUnfavorable

Select the effect.

The new process saves money.The new process costs more money.The new process costs more money.

Enter the overall net amount of the effect. $fill in the blank 13
Select the correct decision.

Discontinue the new process.Continue the new process.Discontinue the new process.

3. Conceptual Connection: Refer to Requirement 2. Suppose that the industrial engineer argued that the new process should not be evaluated after only one week. His reasoning was that it would take at least a week for the workers to become efficient with the new approach. Suppose that the production is the same the second week and that the actual labor hours were 13,000 and the labor cost was $169,000. Should the new process be adopted? Assume the variances are attributable to the new process. Assuming production of 10,000 units per week, what would be the projected annual savings? (Include the materials reduction effect.) If an amount is zero, enter "0".

Rate $fill in the blank 15

FavorableUnfavorableNeitherNeither

Efficiency $fill in the blank 17

FavorableUnfavorableNeitherFavorable

Select the effect.

The new process saves money.The new process costs more money.The new process saves money.

Enter the annual amount of the effect. $fill in the blank 20
Select the correct decision.

Continue the new process.Discontinue the new process.Continue the new process.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Crime Investigation And Control

Authors: K. H. Spencer Pickett, Jennifer M. Pickett

1st Edition

0471203351, 9780471203353

More Books

Students also viewed these Accounting questions