Question
Eden Enterprises (EE) started construction of its office building on August 31, 2013. Treasury department arranged a loan of Rs. 14 million specifically for this
Eden Enterprises (EE) started construction of its office building on August 31, 2013. Treasury department
arranged a loan of Rs. 14 million specifically for this construction on November 30, 2013 from Bank A at
15% per annum.
A contractor was hired for this construction and a total price of Rs. 18 million was agreed. Remaining 4
million were to be financed by an existing running finance carrying markup of 18% per annum. The
contractor submitted the invoices as follows:
Date Value (Rs.)
31-10-13 6,300,000
31-12-13 8,400,000
31-03-14 2,100,000
During 2014, certain changes in design were agreed with contractor which changed the contract price of
building to Rs. 22 million. Due to the requirement of additional funds, management decided to arrange
another loan from Bank B. A loan of Rs. 5 million was arranged on June 1, 2014 at 16.5% per annum. Due
to certain disputes with contractor, construction work was stopped for the month of April 2014. Work
was recommended from start of May 2014 and following invoices were submitted:
Date Value (Rs.)
30-06-14 4,100,000
30-09-14 1,100,000
Construction was completed on September 30, 2014. Contractor invoices were paid one month in arrears.
Surplus funds were kept in a deposit account yielding a return of 6% per annum.
Required: Compute the cost of office building / capital work in progress as at December 31, 2013 and
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started