Edwards Company contracted on 4/1/17. to construct a building for $4,800,000. The project was completed in 2019. Additional data follow: 2017 2018 2019 Costs incurred

Edwards Company contracted on 4/1/17. to construct a building for $4,800,000. The project was completed in 2019. Additional data follow:

2017 2018 2019
Costs incurred to date $1,120,000 $2,700,000 $3,800,000
Estimated cost to complete 2,080,000 900,000 ------
Billings to date 1,000,000 3,800,000 4,800,000
Collections to date 800,000 2,600,000 4,400,000

Instructions

Calculate the income recognized by Edwards under the percentage-of-completion method of accounting in each of the years 2017, 2018, and 2019.

Prepare all necessary entries for the year 2018.

Present the balance sheet disclosures at December 31, 2018. Proper headings or subheadings must be indicated.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting What the Numbers Mean

Authors: David H. Marshall, Wayne W. McManus, Daniel F. Viele,

9th Edition

978-0-07-76261, 0-07-762611-7, 9780078025297, 978-0073527062

More Books

Students also viewed these Accounting questions