Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company's

Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company's needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows:

Supplier

Component 1 2 3

1 $12 $13 $14

2 $10 $11 $10

Each supplier has a limited capacity in terms of the total number of components it can supply. However, as long as Edwards provides sufficient advance orders, each supplier can devote its capacity to component 1, component 2, or any combination of the two components, if the total number of units ordered is within its capacity. Supplier capacities are as follows:

Supplier: 1 2 3

Capacity: 600 1000 800

If the Edwards production plan for the next period includes 1000 units of component 1 and 800 units of component 2, what purchases do you recommend? That is, how many units of each component should be ordered from each supplier?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Tort Law Responsibilities And Redress

Authors: John C. P. Goldberg, Leslie Kendrick, Anthony J. Sebok, Benjamin C. Zipursky

5th Edition

1543806805, 978-1543806809

More Books

Students also viewed these Law questions

Question

Wear as little as possible

Answered: 1 week ago

Question

Be relaxed at the hips

Answered: 1 week ago