egina is a Project Manager at a cracker factory, and is deciding which of three vendors to use to install a new cracker boxing machine.
egina is a Project Manager at a cracker factory, and is deciding which of three vendors to use to install a new cracker boxing machine.
There is a chance that Vendor A can complete the job in weeks, a chance that they will take weeks, and a chance they will take weeks.
Vendor B can deliver and install in weeks if everything 'goes extremely well'...which has a chance of happening. They estimate a chance that there will be 'significant shipping issues' which would result in the project taking weeks. Under all other conditions the project will take weeks.
Finally, Vendor C 'guarantees' installation by week
Regina's goal is to find the vendor with the earliest expected completion time.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started