egina is a Project Manager at a cracker factory, and is deciding which of three vendors to use to install a new cracker boxing machine.

egina is a Project Manager at a cracker factory, and is deciding which of three vendors to use to install a new cracker boxing machine.
There is a 50% chance that Vendor A can complete the job in 7 weeks, a 25% chance that they will take 9 weeks, and a 25% chance they will take 14 weeks.
Vendor B can deliver and install in 5 weeks if everything 'goes extremely well'...which has a 20% chance of happening. They estimate a 40% chance that there will be 'significant shipping issues' which would result in the project taking 18 weeks. Under all other conditions the project will take 11 weeks.
Finally, Vendor C 'guarantees' installation by week 10.
Regina's goal is to find the vendor with the earliest expected completion time.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Ricky W. Griffin

11th edition

111196971X, 978-1111969714

More Books

Students also viewed these General Management questions

Question

Identify related problems that should be addressed.

Answered: 1 week ago