Question
1 Approved Answer

Electralloy Ccorporation data for last month was: queue time was 7 . 8 days, inspection time was 0 . 3 day, process time was 1

Electralloy Ccorporation data for last month was: queue time was 7.8 days, inspection time was 0.3 day, process time was 1.3 days, wait time was 9.7 days, and move time was 0.7 day.
Required:
a. Compute the throughput time.
b. Compute the manufacturing cycle efficiency (MCE).
c. What percentage of the production time is spent in non-value-added activities?
d. Compute the delivery cycle time.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost Accounting A Decision Emphasis

Authors: Germain Boer, Debra Jeter

5th Edition

0759341559, 978-0759341555

More Books

Students explore these related Accounting questions