Question
ell designed WBS helps the project manager in that: a) It defines all the elements of the project in a hierarchical outline (map) b) It
- ell designed WBS helps the project manager in that:
a) It defines all the elements of the project in a hierarchical
outline (map)
b) It defines the relationship of the projectto its subdeliverables,
and in turn, their relationships to work
packages
c) It serves as a framework for tracking cost and work
performance
d) All the above
2.
There are the following advantages to AON method:
a) No dummy activities are used
b) Nodes designate activities
c) Events are not used
d) Easy to draw if dependencies are not intense
e) All of the above
3.
The critical path of a network is the:
a) shortest-time path through the network.
b) path with the fewest activities.
c) path with the most activities.
d) longest-time path through the network.
4.
The crash cost per period:
a) is the difference in costs divided by the difference in times
(crash and normal).
b) is considered to be linear in the range between normal and crash.
c) needs to be determined so that the smallest cost values on
the critical path can be considered for time reduction first.
d) all of the above
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success