Emory Company manufactures wheel rims. The controller expects the following ABC allocation rates for 2018: Activity Allocation Base Predetermined Overhead Allocation Rate Materials Handling Number

Emory Company manufactures wheel rims. The controller expects the following ABC allocation rates for 2018:

Activity Allocation Base Predetermined Overhead Allocation Rate
Materials Handling Number of parts $ 7.00 per part
Machine Setup Number of setups $ 800.00 per setup
Insertion of Parts Number of parts $ 28.00 per part
Finishing Number of finishing hours $ 30.00 per hour

Emory produces two wheel rim models: standard and deluxe. Expected data for 2018 are as follows:

Standard Deluxe
Parts per rim 3.0 10.0
Setups per 500 rims 14.0 14.0
Finishing hours per rim 6.0 6.5
Total direct labor hours per rim 7.0 8.0

Requirement 1. Compute the total estimated indirect manufacturing cost for 2018.

Begin by selecting the formula to compute the total estimated overhead (OH) costs.

X

=

Total estimated overhead costs

Now compute the total estimated indirect manufacturing cost for 2018.

Activity Total Estimated Indirect Manufacturing Cost
Materials handling
Machine setup
Insertion of parts
Finishing
Total Estimated Indirect Manufacturing Cost

Requirement 2. Prior to 2018, Emery used a single plantwide overhead allocation rate system with direct labor hours as the allocation base. Compute the predetermined overhead allocation rate based on direct labor hours for 2018. Use this rate to determine the estimated indirect manufacturing cost per wheel rim for each model, to the nearest cent.

First, write the formula, and then enter the amounts to compute the allocation rate.

/

=

Allocation Rate

/

=

Use the single plantwide allocation rate to determine the indirect manufacturing cost per wheel rim for each model, to the nearest cent.

Indirect manufacturing cost per rim:

Standard Model: ____________

Deluxe Model: ______________

Requirement 3. Compute the estimated ABC indirect manufacturing cost per unit of each model for 2018. Carry each cost to the nearest cent.

Compute the costs per unit for the standard model first, then the deluxe model. (Carry the setup cost per rim to three decimal places. Round your final answers to the nearest cent.)

Allocated Mfg. OH Cost Per Rim Allocated Mfg. OH Cost Per Rim
Activity Standard Deluxe
Materials handling
Machine setup
Insertion of parts
Finishing
Total cost per rim

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing CPA Exam Review

Authors: Becker

1st Edition

1943628696, 978-1943628698

More Books

Students also viewed these Accounting questions