Question

1 Approved Answer

Lloyd Systems Ltd is considering the possibility of launching a new ICT project to improve its internal connectivity and organizational productivity. Past corporate performance from

Lloyd Systems Ltd is considering the possibility of launching a new ICT project to improve its internal connectivity and organizational productivity. Past corporate performance from revenue on statistics confirm a rapid decline on productivity. As an ICT consultant engaged by Lloyd Systems Ltd, you are required to:

(a) Identify and explain three (3) major tenets of this project when preparing a business case                                                                    
EV (7 marks)
(b) Assume that project sponsors of Lloyd Ltd has agreed to finance the new ICT project after viable project appraisal, state three (3) major components to be addressed in your project scope                                                                                                    
(c) How would you ensure that new ICT project requirements translate into project success?                                                                                                    

Question 2

Figure 1 provides a Gantt Chart with schedule activities on a 3-year National Youth Employment Project in Ghana. The project has three major components out of which detailed schedule has been prepared on a Gantt Chart. You are required to use Figure 1 to address the following questions:
(a) What is the significance of the thick black lines corresponding to the project components in scheduling the National Youth Employment Project?                                

(b) Critically examine Figure 1 and explain the weakness in the Gantt Chart which can affect correct determination of critical activities on the National Youth Employment Project.

(c) Explain how you will monitor and control the National Youth Employment Project activities      

Figure 1. Gantt Chart on a 3-year National Youth Employment Project in Ghana
Question 3

By relying on detailed activities provided in Figure 1 on the National Youth Employment Project, you are required to perform the following activities under component 1, 2 and 3:
(a) Prepare a total project budget within a range of 500,000 to 1,000,000 Ghana Cedis.                              
(b) Given that about 50% of activities have been undertaken on component 1 and 2, determine with the aid of appropriate Table or Chart your cost variances and explain their relevance in project cost tracking.                                                                    
(c) Determine all the remaining costs on component 2 and 3 of the National Youth Employment Project in Tabular form and explain their significance    


Question 4

You have recently been engaged as a Project Manager to ensure effective implementation of a capacity building of project being sponsored by the World Bank to improve staff productivity at Ghana Water Company Ltd with focus on ICT and engineering trainings. The three (3) major project components are as follows:

Component 1: Institutional Reorganization and Change Management 

Component 2: Staff Training and Technology Transfer
Component 3: Project Monitoring & Controlling, Evaluation & Reporting
You are required to use the information above to:
(a) Identify six major tasks to be undertaken on the project.        
(b) Prepare a detailed project work breakdown structure with major tasks and sub-tasks

(c) Explain how you will use the Gantt Chart to prepare a schedule on activities earmarked for implementation on the capacity building improvement project at Ghana water Company Ltd.                                                                          
Question 5
a) As part of a nation-wide intervention efforts to minimize deforestation in Ghana to combat the adverse effect of climate change, the Forestry Commission has entered into partnership with Eco-green Ghana, a Civil Society
Organization in the business of championing greening of the environment to undertake tree planting across five (5) pilot districts in Ghana. The Districts are Bongo East, Karaga, Nanumba, Chereponi and Nadowli. The project
components are as follows:

Component 1: Community Sensitization, Gathering of Seedlings and Recruitment of Tree Planters

Component 2: Training of Tree Planters and Assignment of Tasks

Component 3: Monitoring, Evaluation and Reporting

You are required to use the information provided on the tree planting project to:

(a) Develop a matrix that can monitor the project activities. Limit yourself to one project objective and a minimum of five main activities and indicators;                


(b) Develop a risk management plan to track your project activities;            

(c) Explain your approach to risk communication on the afforestation project to key stakeholders.    

Step by Step Solution

3.40 Rating (159 Votes )

There are 3 Steps involved in it

Step: 1

a Major Tenets of ICT project when preparing a business case are 1 Use ICT to Support Datadriven Decision Making Regular and reliable data are essential to planning and policy financial management man... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel,

7th Edition

470226218, 978-0470226216

More Books

Students also viewed these Computer Network questions