Energizer Cements Private Ltd. produces and sells one product only, E7 cement, the standard cost for one unit being as follows. Direct material - 10
Energizer Cements Private Ltd. produces and sells one product only, E7 cement, the standard cost for one unit being as follows.
Direct material - 10 kilograms at 20 per kg | 200 |
Direct wages - 5 hours at 6 per hour | 30 |
Variable production overhead - 5 hours at 1 per hour | 5 |
Fixed production overhead - 5 hours at 10 per hour | 50 |
Total standard cost | 285 |
The fixed production overhead included in the standard cost is based on an expected monthly output of 900 units. | |
During October 2021 the actual results were as follows. | |
Production | 800 units |
Direct material | 7,800 kg used, costing 159,900 |
Direct wages | 3,800 hours worked for 24,150 |
Variable production overhead | 4,900 |
Fixed production overhead | 47,000 |
Required:
- Flex the original budget and show the variances between the flexible budget and actual results (6 marks)
- Calculate the following variances:
- Direct material price and usage variances
- Direct labour rate and efficiency variances
(14 marks)
- Discuss the reasons for the adverse/unfavourable variances and provide recommendations to improve (15 marks)
- Discuss the behavioural implications of allowing staff to participate in the budget setting process (15 marks)
(Total: 50 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started