Engineering Economics: Geometric Gradient Cash Flows What is wrong with my solution below? There is a discrepancy in the value when computing each single cash
Engineering Economics: Geometric Gradient Cash Flows
What is wrong with my solution below?
There is a discrepancy in the value when computing each single cash flow to EOY- 0 which is seen below:
3. Determine the present equivalent (at time zero) of the following geometric sequence of cash flows. Let i=15.5% jer year and f=10%. Strictly using geometric gradient. P=(A3[ig1(1+i1+g)N])(1+i)2=((1,000)[0.1550.11(1.1551.1)22])(1.155)2 3. Determine the present equivalent (at time zero) of the following geometric sequence of cash flows. Let i=15.5% jer year and f=10%. Strictly using geometric gradient. P=(A3[ig1(1+i1+g)N])(1+i)2=((1,000)[0.1550.11(1.1551.1)22])(1.155)2Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started