Question

1 Approved Answer

engineering economics question. chegg's solutuon answer was 2250$ but i believe its wrong. can someone confirm. thanks 3. Assume that overhead is charged on a

engineering economics question.
chegg's solutuon answer was 2250$ but i believe its wrong. can someone confirm.
thanks
image text in transcribed
image text in transcribed
3. Assume that overhead is charged on a flat-rate basis. Each mem- ber of the project is assigned an overhead charge of $150/week. What would the direct cost of labor be for an employee, given that she is assigned to the project for 200 hours at $10.50/hour? overhead charge - $ 150/week or 150/168 200 hours at 10.5 fully looded D (10.5)(200) + 178.5753 2278.57 Cost 168hrs lween 200he ZX 260 hrs -D 1.19 weeks 168hrs 150$ Rohrs (x= 178,57$

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Investing

Authors: Scott B. Smart, Lawrence J. Gitman, Michael D. Joehnk

14th Edition

0135175216, 978-0135175217

More Books

Students also viewed these Finance questions

Question

Define indirect financial compensation (employee benefits).

Answered: 1 week ago

Question

Describe the selection decision.

Answered: 1 week ago