Question
Engineering project Given the following $3,000,000 Architectural/Engineering (A/E) design and construction management project for a new high school building (containing 2 floors and approximately 260,000
Engineering project
Given the following $3,000,000 Architectural/Engineering (A/E) design and construction management project for a new high school building (containing 2 floors and approximately 260,000 square feet) create a WBS (in ALL 4 separate formats: Outline View, Hierarchical Structure, Tabular View, and Tree Structure View - the University provided template MUST be used) to at least Level 3 (include the project, deliverables, activities and work packages) for the project based on the areas provided:
- The upcoming A/E design and construction managementproject has the following project management areas:
- Schematic Design
- Design Development
- Construction Documentation
- Bidding Phase Services
- Construction Administration Phase
- Project Closeout
- Project Management
Work Breakdown Structure (WBS)
And
WBS Dictionary
Name of Student
Date Submitted:
Note for students: TheGREEN text is for your information only in completing this template. Remove theGREEN guidance before submission of this assignment deliverable. Replace with your own text relative to the chosen assignment case study. .
For this assignment Norwich students will complete the outline view, hierarchical view, tabular view, the tree view and a WBS dictionary to WBS level three. Ensure WBS ID numbers are included for each element in the WBS's.Ensure funding is appropriately allocated to each element in your WBSs adhering to the 100% rule.
REMOVE THIS RED TEXT ALSO BEFORE SUBMISSION
Introduction
The WBS is a view into the project which shows what work the project encompasses. It is a tool which helps to easily communicate the work and processes involved to execute the project. The Project Manager and project team use the WBS to develop the project schedule, resource requirements and costs. There are many ways you can present the WBS for your project; this template provides many of the most popular layouts from which you can choose.Depending on where in the Project Plan you're putting the WBS a different layout may be more suitable.For instance many Project Managers include a high level WBS within the project plan, then a detailed version as an appendix to the plan. You may find that you prefer one layout for a high level WBS and a different one for a detailed WBS.
The Work Breakdown Structure presented here represents all the work required, AND ONLY THE WORK REQUIRED, to complete this project.
Outline View
The outline view presents an easy to view and understand layout for the WBS. It is also a good layout to use when developing the WBS because you can easily make changes, especially since the Microsoft Word auto numbering feature updates the WBS Code automatically. The outline format is recommended for larger projects. Ensure budget is allocated adhering to the 100% rule.
- Name of Project ($XXX,XXX)
2.1.Title of Phase/ Sub-system / Major Deliverable ($XX,XXX)
2.1.1.Activity A ($XX,XXX)
- Activity B ($XX,XXX)
2.1.3. Activity C ($XX,XXX)
2.1.4. Deliverable: (name of deliverable)
2.1.5. Milestone:(name of milestone event)
- Title of Phase/ Sub-system / Major Deliverable ($XX,XXX)
- Activity A ($XX,XXX)
- Activity B ($XX,XXX)
- Activity C ($XX,XXX)
- Activity D ($XX,XXX)
- Activity E (SXX,XXX)
- Activity F ($XX,XXX)
- Deliverable: (name of deliverable
- Milestone: Name of Milestone
4..1 Title of Phase / Sub-system / Major Deliverable ($XXX,XXX)
- Activity A ($XX,XXX)
- Activity B ($XX,XXX)
- Activity C ($XX,XXX)
- Activity D ($XX,XXX)
- Activity E ($XX,XXX)
- Deliverable: (name of deliverable
- Milestone: (name of milestone event)
- Name of Phase / Sub-system / Major Deliverable ($XXX,XXX)
- Activity A ($XX,XXX)
- Activity B ($XX,XXX)
- Activity C ($XX,XXX)
- Activity D ($XX,XXX)
- Deliverable: (name of deliverable
- Milestone:(name of milestone event)
- Name of Phase / Sub-system / Major Deliverable ($XX,XXX)
- Activity A ($XX,XXX)
- Activity B ($XX,XXX)
- Activity C ($XX,XXX)
- Activity D ($XX,XXX)
- Deliverable: (name of deliverable
- Milestone:Name of milestone event
7.1. Name of Phase/ Sub-system / Major Deliverable ($XX,XXX)
- Activity A ($XX,XXX)
- Activity B ($XX,XXX)
- Activity C ($XX,XXX)
- Activity C ($XX,XXX)
- Deliverable: (name of deliverable)
- Milestone: (Name of milestone event)
- Project Management ($XX,XXX)
- Activity A ($XX,XXX)
- Activity B ($XX,XXX)
- Activity C ($XX,XXX)
- Activity D ($XX,XXX)
- Deliverable: name of deliverable
Hierarchical Structure
The hierarchal structure is similar to the outline view but without indentation. Although this format is more difficult to read, it may be useful where you have many levels and indenting each level would make the table too large to fit into a document.
Level | WBS Code | Element Name | Budget Allocated |
1 | 1 | Name of Project | |
2 | 2.1. | Name of Phase/ Sub-system / Major Deliverable | |
3 | 2.1.1 | Activity A | |
3 | 2.1.2 | Activity B | |
3 | 2.1.3 | Activity C | |
2 | 3.1. | Name of Phase/ Sub-system / Major Deliverable | |
3 | 3.1.1 | Activity A | |
3 | 3.1.2 | Activity B | |
3 | 3.1.3 | Activity C | |
3 | 3.1.4 | Activity D | |
3 | 3.1.5 | Activity E | |
3 | 3.1.6 | Activity F | |
2 | 4.1 | Name of Phase/ Sub-system / Major Deliverable | |
3 | 4.1.1. | Activity A | |
3 | 4.1.2 | Activity B | |
3 | 4.1.3 | Activity C | |
3 | 4.1.4 | Activity D | |
3 | 4.1.5 | Activity E | |
2 | 5.1 | Name of Phase/ Sub-system / Major Deliverable | |
3 | 5.1.1. | Activity A | |
3 | 5.1.2 | Activity B | |
3 | 5.1.3 | Activity C | |
3 | 5.1.4 | Activity D | |
2 | 6.1 | Name of Phase/ Sub-system / Major Deliverable | |
3 | 6.1.1. | Activity A | |
3 | 6.1.2 | Activity B | |
3 | 6.1.3 | Activity C | |
3 | 6.1.4 | Activity D | |
2 | 7.1 | Name of Phase/ Sub-system / Major Deliverable | |
3 | 7.1.1. | Activity A | |
3 | 7.1.2 | Activity B | |
3 | 7.1.3 | Activity C | |
2 | 8.1 | Project Management | |
3 | 8.1.1. | Activity A | |
3 | 8.1.2 | Activity B | |
3 | 8.1.3 | Activity C | |
3 | 8.1.4 | Activity D |
Tabular View
The Tabular View is a nicely organized table view of the WBS. It is a good option for organizations which prefer table formats.
Level 1 | Level 2 | Level 3 | Budget Allocation |
1Name of Project | 2.1 Name of Phase/ Sub-system / Major Deliverable | 2.1.1 Activity A 2.1.2 Activity B 2.1.3 Activity C | 2.1.1 2.1.2 2.1.3 |
3.1 Name of Phase/ Sub-system / Major Deliverable | 3.1.1 Activity A 3.1.2 Activity B 3.1.3 Activity C 3.1.4 Activity D 3.1.5 Activity E 3.1.6 Activity F | 3.1.1. 3.1.2 3.1.3 3.1.4 3.1.5 3.1.6 | |
4.1 Name of Phase/ Sub-system / Major Deliverable | 4.1.1 Activity A 4.1.2 Activity B 4.1.3 Activity C 4.1.4 Activity D 4.1.5 Activity E | 4.1.1. 4.1.2 4.1.3 4.1.4 4.1.5 | |
5.1. Name of Phase/ Sub-system / Major Deliverable | 5.1.1 Activity A 5.1.2 Activity B 5.1.3 Activity C 5.1.4 Activity D | 5.1.1 5.1.2 5.1.3 5.1.4 | |
6.1 Name of Phase/ Sub-system / Major Deliverable | 6.1.1 Activity A 6.1.2 Activity B 6.1.3 Activity C 6.1.4 Activity D | 6.1.1 6.1.2 6.1.3. 6.1.4 | |
7.1 Name of Phase/ Sub-system / Major Deliverable | 7.1.1 Activity A 7.1.2 Activity B 7.1.3 Activity C | 7.1.1. 7.1.2 7.1.3 | |
8.1 Name of Phase/ Sub-system / Major Deliverable | 8.1.1 Activity A 8.1.2 Activity B 8.1.3 Activity C 8.1.4 Activity D | 8.1.1. 8.1.2 8.1.3 8.1.4 |
Tree Structure View
The Tree Structure View is the most popular format for the WBS. It presents an easy to understand view into the WBS; however, it is also tricky to create without an application specifically designed for creating this organizational chart structure. The Tree Structure below was created using only Microsoft Word and the SmartArt graphics option under the insert menu.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started