Question
Entity A is a local contractor listed in Hong Kong for many years. It entered into a contract with the government on 1 January 2021
-
Entity A is a local contractor listed in Hong Kong for many years. It entered into a contract with the government on 1 January 2021 to build a cross-harbour tunnel.
The total contract revenue was $5,600,000. On 31 December 2021, the contract was certified as 35% complete. Costs incurred during the year were $1,480,000 and costs to complete are estimated at $2,800,000. The amount of $1,400,000 has been billed to the government but not yet paid.
REQUIRED:
Evaluate the amount of Contract Asset or Contract Liability that will be recognised in the Statement of Financial Position on 31 December 2021.
1. None of them.
2. $1,018,000 Contract Asset
3. $542,000 Contract Asset
4. $542,000 Contract Liability
5. $1,018,000 Contract Liability
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started