Question

1 Approved Answer

Entries and Schedules for Unfinished Jobs and Completed Jobs Tybee Industries Inc. uses a job order cost system. The following data summarize the operations related

  1. Entries and Schedules for Unfinished Jobs and Completed Jobs

    Tybee Industries Inc. uses a job order cost system. The following data summarize the operations related to production for January, the first month of operations:

    1. Materials purchased on account, $2,910.
    2. Materials requisitioned and factory labor used:
      Job Materials Factory Labor
      301 $2,240 $2,030
      302 2,730 2,740
      303 1,810 1,340
      304 6,140 5,030
      305 3,900 3,840
      306 2,840 2,440
      For general factory use 760 3,000
    3. Factory overhead costs incurred on account, $4,280.
    4. Depreciation of machinery and equipment, $1,440.
    5. The factory overhead rate is $35 per machine hour. Machine hours used:
      Job Machine Hours
      301 36
      302 43
      303 15
      304 72
      305 36
      306 26
      Total 228
    6. Jobs completed: 301, 302, 303, and 305.
    7. Jobs were shipped and customers were billed as follows: Job 301, $6,640; Job 302, $8,370; Job 303, $10,660.

    Required:

    1. Journalize the entries to record the summarized operations. For a compound transaction, if an amount box does not require an entry, leave it blank.

    Entries Description Debit Credit
    a. fill in the blank 2
    fill in the blank 4
    b. fill in the blank 6 fill in the blank 7
    fill in the blank 9 fill in the blank 10
    fill in the blank 12 fill in the blank 13
    fill in the blank 15 fill in the blank 16
    c. fill in the blank 18
    fill in the blank 20
    d. fill in the blank 22
    fill in the blank 24
    e. fill in the blank 26
    fill in the blank 28
    f. fill in the blank 30
    fill in the blank 32
    g. fill in the blank 34
    fill in the blank 36
    fill in the blank 38
    fill in the blank 40

    2. Post the appropriate entries to T accounts for Work in Process and Finished Goods, using the identifying letters as transaction codes. Insert memo account balances as of the end of the month.

    Work in Process
    fill in the blank 42 fill in the blank 44
    fill in the blank 46
    Bal. fill in the blank 47
    Finished Goods
    fill in the blank 49 fill in the blank 51
    Bal. fill in the blank 52

    3. Prepare a schedule of unfinished jobs to support the balance in the work in process account.

    Tybee Industries Inc. Schedule of Unfinished Jobs
    Job Direct Materials Direct Labor Factory Overhead Total
    $ fill in the blank 54 $ fill in the blank 55 $ fill in the blank 56 $ fill in the blank 57
    fill in the blank 59 fill in the blank 60 fill in the blank 61 fill in the blank 62
    Balance of Work in Process, January 30 $ fill in the blank 63

    4. Prepare a schedule of completed jobs on hand to support the balance in the finished goods account.

    Tybee Industries Inc. Schedule of Completed Jobs
    Job Direct Materials Direct Labor Factory Overhead Total
    $ fill in the blank 65 $ fill in the blank 66 $ fill in the blank 67 $ fill in the blank 68

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Public Sector Audit

Authors: Carolyn J. Cordery, David C. Hay

1st Edition

0367650622, 9780367650629

More Books

Students also viewed these Accounting questions