Entries and Schedules for Unfinished Jobs and Completed Jobs Tybee Industries Inc. uses a job order cost system. The following data summarize the operations related

Entries and Schedules for Unfinished Jobs and Completed Jobs

Tybee Industries Inc. uses a job order cost system. The following data summarize the operations related to production for January, the first month of operations:

Materials purchased on account, $1,870.

Materials requisitioned and factory labor used:

Job Materials Factory Labor
301 $2,300 $2,400
302 2,810 3,240
303 1,860 1,580
304 6,300 5,950
305 4,000 4,540
306 2,920 2,880
For general factory use 780 3,550

Factory overhead costs incurred on account, $4,390.

Depreciation of machinery and equipment, $1,700.

The factory overhead rate is $40 per machine hour. Machine hours used:

Job Machine Hours
301 36
302 15
303 42
304 74
305 38
306 41
Total 246

Jobs completed: 301, 302, 303, and 305.

Jobs were shipped and customers were billed as follows: Job 301, $7,370; Job 302, $7,980; Job 303, $14,850.

Required:

1. Journalize the entries to record the summarized operations. For a compound transaction, if an amount box does not require an entry, leave it blank.

Entries Description Debit Credit
a. Materials
Accounts Payable
b. Work in Process
Factory Overhead
c. Factory Overhead
Accounts Payable
d. Factory Overhead
Accumulated Depreciation-Machinery and Equipment
e. Work in Process
Factory Overhead
f. Finished Goods
Work in Process
g. Accounts Receivable
Sales
Cost of Goods Sold
Finished Goods

2. Post the appropriate entries to T accounts for Work in Process and Finished Goods, using the identifying letters as transaction codes. Insert memo account balances as of the end of the month.

Work in Process
(b) (f)
(e)
Bal.

Finished Goods
(f) (g)
Bal.

3. Prepare a schedule of unfinished jobs to support the balance in the work in process account.

Tybee Industries Inc. Schedule of Unfinished Jobs
Job Direct Materials Direct Labor Factory Overhead Total
No. 304 $ $ $ $
No. 306
Balance of Work in Process, January 30 $

4. Prepare a schedule of completed jobs on hand to support the balance in the finished goods account.

Tybee Industries Inc. Schedule of Completed Jobs
Job Direct Materials Direct Labor Factory Overhead Total
Finished Goods, January 30 (Job 305) $ $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Bank Management Text And Cases

Authors: George H. Hempel, Alan B. Coleman, Donald G. Simonson

3rd Edition

0471621781, 978-0471621782

More Books

Students also viewed these Accounting questions

Question

15.7 Explain the six steps in the termination interview

Answered: 1 week ago

Question

15.1 Define employee relations and employee engagement.

Answered: 1 week ago