Question
Entries and Schedules for Unfinished Jobs and Completed Jobs Tybee Industries Inc. uses a job order cost system. The following data summarize the operations related
Entries and Schedules for Unfinished Jobs and Completed Jobs Tybee Industries Inc. uses a job order cost system. The following data summarize the operations related to production for January, the first month of operations: Materials purchased on account, $2,290. Materials requisitioned and factory labor used:
Job | Materials | Factory Labor | ||
301 | $2,620 | $2,050 | ||
302 | 3,200 | 2,770 | ||
303 | 2,120 | 1,350 | ||
304 | 7,180 | 5,080 | ||
305 | 4,560 | 3,870 | ||
306 | 3,330 | 2,460 | ||
For general factory use | 890 | 3,030 |
Factory overhead costs incurred on account $5,000 depreciation of machinery and equipment $1,460 the factory overhead rate is $70 per machine hour. Machine hours used:
Job | Machine Hours | ||
301 | 40 | ||
302 | 20 | ||
303 | 15 | ||
304 | 70 | ||
305 | 39 | ||
306 | 28 | ||
Total | 212 |
jobs completed 301,302,303, and 305
jobs were chipped and customers were billed as follows: job 301 $ $8,960; Job 302, $8,840; Job 303, $13,110
1. Journalize the entries to record the summarized operations. For a compound transaction, if an amount box does not require an entry, leave it blank.
Entries | Description | Debit | Credit |
---|---|---|---|
a. | Materials | ||
Accounts Payable | |||
b. | Work in Process | ||
Factory Overhead | |||
Materials | |||
Wages Payable | |||
c. | Factory Overhead | ||
Accounts Payable | |||
d. | Factory Overhead | ||
Accumulated Depreciation-Machinery and Equipment | |||
e. | Work in Process | ||
Factory Overhead | |||
f. | Finished Goods | ||
Work in Process | |||
g. | Accounts Receivable | ||
Sales | |||
Cost of Goods Sold | |||
Finished Goods |
2. Post the appropriate entries to T accounts for Work in Process and Finished Goods, using the identifying letters as transaction codes. Insert memo account balances as of the end of the month.
Work in Process | |||
---|---|---|---|
(b) | (f) | ||
(e) | |||
Bal. |
Finished Goods | |||
---|---|---|---|
(f) | (g) | ||
Bal. |
3. Prepare a schedule of unfinished jobs to support the balance in the work in process account.
Tybee Industries Inc. Schedule of Unfinished Jobs | ||||||||
---|---|---|---|---|---|---|---|---|
Job | Direct Materials | Direct Labor | Factory Overhead | Total | ||||
No. 304 | $ | $ | $ | $ | ||||
No. 306 | ||||||||
Balance of Work in Process, January 30 | $ |
4. Prepare a schedule of completed jobs on hand to support the balance in the finished goods account.
Tybee Industries Inc. Schedule of Completed Jobs | ||||||||
---|---|---|---|---|---|---|---|---|
Job | Direct Materials | Direct Labor | Factory Overhead | Total | ||||
Finished Goods, January 30 (Job 305) | $ | $ | $ | $ |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started