Entry for Jobs Completed; Cost of Unfinished Jobs The following account appears in the ledger prior to recognizing the jobs completed in January: Work in
Entry for Jobs Completed; Cost of Unfinished Jobs
The following account appears in the ledger prior to recognizing the jobs completed in January:
Work in Process | ||
Balance, January 1 | $10,690 | |
Direct materials | 86,910 | |
Direct labor | 93,750 | |
Factory overhead | 49,280 |
Jobs finished during January are summarized as follows:
Job 210 | $43,310 |
Job 216 | 26,470 |
Job 224 | 50,530 |
Job 230 | 91,440 |
a. Journalize the entry to record the jobs completed. If an amount box does not require an entry, leave it blank.
fill in the blank 0b2f57f79f91fcd_2 | fill in the blank 0b2f57f79f91fcd_3 | ||
fill in the blank 0b2f57f79f91fcd_5 | fill in the blank 0b2f57f79f91fcd_6 |
b. Determine the cost of the unfinished jobs at January 31. $fill in the blank 684c8a058fee04d_1
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started